Work plan

The RESILIENCE work plan is structured around four tightly connected Work Packages that link catalyst innovation, electrified microwave reactor design, and quantitative efficiency assessment. The structure ensures that materials development, reactor implementation, and performance evaluation progress in a coordinated manner, while project management and dissemination activities run in parallel to support impact and Open Science.

Work Packages

WP Title Duration
WP1 Synthesis of novel catalysts Months 1–30
WP2 Design and implementation of electrified reactors Months 1–24
WP3 Efficiency assessment of electrified reactors Months 13–36
WP4 Project management and dissemination activities Months 1–36

Timeline

  • Start: 03 November 2025
  • End: 02 November 2028
  • Duration: 36 months
Public deliverables and publications will be listed under Results. Updates and announcements will appear in News.